Chaffey Dam Safety Upgrade and Augmentation

Completed in 2016, the upgrade of the regional Chaffey Dam near Tamworth involved raising the existing dam wall by eight metres and the mouth of the ‘morning glory’ spillway by 6.5 metres, increasing storage capacity from 62,000 to 100,500 megalitres.

The downstream embankment was also strengthened, and an auxiliary spillway constructed to enable the dam to safely pass rare and extreme floods.

Customer
WaterNSW
Location
New England, New South Wales
Specialisation
Water & wastewater
End
2016